The next Dacorum Local Plan consultation now runs 8 July to 2 September 2027, after the May elections. The 30 April 2029 adoption date is unchanged.

The next public consultation on Dacorum’s new Local Plan has been put back by two months. It will now run from 8 July to 2 September 2027, instead of 7 May to 18 June.

The reason is the borough elections next May. The council’s planning chief made the change on 13 November, and it was published on 16 November (Dacorum Borough Council, decision record).

The end date has not moved. The plan is still due to go to the government for examination on 22 October 2028 and to be adopted on 30 April 2029.

Overview

  • The “plan content and evidence” consultation moves from 7 May to 18 June 2027 to 8 July to 2 September 2027.
  • It grows from six weeks to eight.
  • The consultation on the proposed plan itself moves from February to April 2028 to 20 April to 15 June 2028.
  • Submission (22 October 2028) and adoption (30 April 2029) stay the same.

Why the dates changed

The original May date was set when the borough expected elections to a new shadow authority on 6 May 2027. That was part of the plan to merge Dacorum and St Albans into a West Hertfordshire Council.

The government paused that reorganisation in September. The officer decision record says that “means that local elections are now scheduled for Dacorum next May” (officer decision record, PDF).

Draft Local Plan material has to be approved by Cabinet or Full Council before it goes out to consultation. With an election in May, the record says, “there is uncertainty over the timescale” for that approval. Keeping the old date would also have put the consultation inside the pre-election period, which the council’s own guidance rules out.

There is a second reason. Dacorum’s current plan, the Local Plan to 2041, is still at examination, and the inspectors set its timetable. The record warns that a consultation on changes to that plan “could clash” with the next round on the new one. Two consultations on two separate plans at once “risks confusion and criticism from local communities”.

The council rejected bringing the consultation forward for the same reason.

The new timetable

Stage Old date New date
Plan content and evidence consultation 7 May to 18 June 2027 8 July to 2 September 2027
Gateway 2: advice sought 6 August 2027 22 October 2027
Proposed plan consultation 17 February to 13 April 2028 20 April to 15 June 2028
Gateway 3: advice sought 22 June 2028 17 August 2028
Submitted for examination 22 October 2028 22 October 2028
Adopted 30 April 2029 30 April 2029

Source: Dacorum Borough Council officer decision record, 13 November 2026. The gateways are checks by the Planning Inspectorate under the new plan-making rules.

The earlier stages are unchanged. The scoping consultation ran from 11 September to 2 October 2026, and Gateway 1 was on 31 October.

Officers say they found “efficiencies later in the timetable”, so the government’s 30-month deadline is not affected. In practice the squeeze falls at the end. The gap between Gateway 3 and submission shrinks from four months to just over two.

The decision was taken by the Assistant Director for Planning, Ross Whear, under powers Cabinet delegated in June to keep the timetable up to date. It was not subject to call-in. The council’s legal officer notes that this is a decision about dates only. Approving the draft plan itself is still a matter for Cabinet or Full Council.

What it means for you

If you want a say on what goes into the new plan, your next chance is now in the summer of 2027, after the borough elections. It is also two weeks longer than before.

Nothing about where homes could go has been decided. The call for sites closed on 23 October, and the stages of the Local Plan to 2045 still run to April 2029.

The council’s Future Local Plan page carries the timetable. The new rules require it to be kept under review, so these dates can still move.