Dacorum has approved up to £350,000 to tarmac the potholed track into Bunkers Park and extend its 15-space car park. No start date has been given.

The potholed track into Bunkers Park is to be tarmacked and its small car park extended. Dacorum Borough Council approved the works on Tuesday 10 November, at a value of up to £350,000.

The decision was published the same day as an officer decision record signed by the council’s Strategic Director for Environment. No start date or programme has been published.

What is being built

The park, in the south-east corner of Hemel Hempstead off Bedmond Road, has one car park with room for about 15 cars. The council’s decision paper says the track is tarmacked only as far as the entrance to the Poppy Fields Cemetery car park. The last 150 metres or so, up to and including the park’s own car park, is compacted stone. About 25 more cars park informally along the track.

The paper sets out four pieces of work:

  • the access road upgraded to tarmac, with speed restrictors
  • the car park extended and surfaced in tarmac
  • marked bays, including spaces for disabled visitors
  • a cycle rack in the car park

The paper does not say how many spaces the extended car park will have.

Why the council is doing it

The paper is blunt about the current state of the place. The track “becomes potholed through use and requires regular maintenance”. In winter, parts of the waymarked routes and the ground around the car park “become very muddy and difficult for walkers to access”. Combined with the small number of spaces, the council says, this makes the park “unattractive to visitors”.

That matters for a reason beyond the potholes. Bunkers Park is one of Dacorum’s Suitable Alternative Natural Greenspace (SANG) sites, along with Chipperfield Common. These are green spaces improved on purpose to draw walkers away from the Ashridge Commons and Woods, part of the Chilterns Beechwoods Special Area of Conservation.

Under the council’s mitigation strategy, approved by Cabinet in November 2022, new housing has to pay towards that protection. Developers can buy capacity at a council SANG instead of providing their own. The paper says developers have bought credits assigned to Bunkers Park, and that failing to deliver the agreed improvements would open the council to legal challenge from them. The same strategy lies behind the National Trust’s new car park at Ashridge, approved earlier this month.

The management plan for the park was agreed by the council and Natural England in November 2022. The deputy finance officer’s note says the contract “is in line with SANG delivery expectations and funding”.

Who will do the work

The job goes straight to Ringway, Hertfordshire County Council’s highways contractor, without a separate tender. Dacorum uses the county’s existing term contract, which names the borough council as able to use it. Ringway also drew up the design, after being appointed in January 2026.

The paper accepts that this “does not provide direct competition for this specific package of works” and that a management fee is payable to the county council. It argues the saving in officer time and the quicker start outweigh that.

Nash Mills Parish Council and the ward councillors for Nash Mills and Leverstock Green were consulted, according to the record.

What it means for you

If you walk at Bunkers Park, expect the car park and the track from Bedmond Road to be dug up at some point, though the council has not said when. The cemetery car park shares the first stretch of the track, so visitors to Poppy Fields may see the works too.

Once finished, the tarmac track should need less patching, and there will be more marked spaces, including disabled bays, and somewhere to lock a bike.

We will add the start date and the number of new spaces when the council publishes them.