Dacorum councillors voted 5-3, with two abstentions, to back up to 700 homes on Green Belt north of Polehanger Lane. Permission waits on a legal agreement and a call-in check.
Dacorum’s Development Management Committee has backed plans for up to 700 homes on Green Belt farmland north of Polehanger Lane, on the north-western edge of Hemel Hempstead.
Updated 5 November: the published minutes of the 15 October meeting confirm the vote of 5 for, 3 against and 2 abstentions.
The vote on Thursday 15 October was five in favour, three against, with two abstentions. The chair announced the result at the end of a debate lasting more than two hours. It is on the council’s own webcast of the meeting (Dacorum Borough Council, webcast, vote at 2:30:18). The written minutes have not yet been published.
Councillor Claire Hobson proposed the officers’ recommendation and Councillor Brian Patterson seconded it. The chair named Councillors Angela Mitchell and Andrew Williams as the two who abstained.
Approved, but not yet permission
The committee did not grant planning permission outright. It voted for the officers’ recommendation that the application, reference 25/01742/MOA, be “delegated with a view to approval” (committee report, item 5a).
Officers can issue the permission only once three things are done:
- a final habitats assessment for the Chilterns Beechwoods Special Area of Conservation, with a mitigation package secured
- the Section 106 legal agreement is signed by the developer, the landowners and the councils
- the Secretary of State confirms the application will not be called in. Major development approved in the Green Belt has to be referred to the government’s Planning Casework Unit
So no homes can be built yet, and the layout, house designs and school design all still need separate applications.
Two conditions added on the night
The planning officer told the committee that two changes to the conditions had been proposed in the debate, and that officers were satisfied both could be added:
- Condition 17, the construction traffic plan, will look at restricting large lorries, or reducing their numbers, driving through Potten End
- Condition 12 will require further archaeological investigation, which Councillor Mitchell raised
Why officers said yes
The site is Green Belt, and officers accepted the scheme is “inappropriate development” there. Their case was that Dacorum’s housing shortfall amounts to the “very special circumstances” needed to outweigh that harm.
The report puts the council’s deliverable housing supply at about 1.2 years, against the five years the government requires. Summing up on Thursday, the officer called that position “very dire”. The site is also allocated for about 750 homes in the council’s emerging Local Plan, which is still with the government’s inspectors.
One councillor who spoke against said the site had been added to the emerging Local Plan late, and that approving it before the inspectors report runs against the government’s wish for a “plan-led system”.
What the scheme includes
The report lists:
- up to 700 homes, at least 40 per cent of them affordable, which the officer put at 280 homes
- an extra-care home of up to 66 units and a children’s home for up to three children
- a two-form-entry primary school with a nursery
- a neighbourhood centre with shops and community space
- 16.4 hectares of natural greenspace and 9 hectares of public open space
- a new roundabout on Berkhamsted Road, which is the only access
The Section 106 agreement carries the money for off-site works. The largest sums are below; our preview of the committee meeting lists the rest.
What it means for you
- If you objected, the committee’s vote is not the last step. The government decides whether to call the application in, and that is the only route to a fresh decision before permission is issued.
- If you live in Gadebridge or Warners End, the first visible change would be the Berkhamsted Road roundabout. The report’s own timetable has the first 10 homes finished in 2028/29 and building running for about a decade.
- If you are waiting for a council or housing association home, up to 280 affordable homes are promised, 70 per cent of them for rent.
All the application documents and comments are on the council’s planning register. From 31 October most smaller applications in Dacorum will be decided by officers rather than councillors, as we explained in our story on the planning call-in changes. More on live schemes is on our Hemel Hempstead planning news page.
Sources
- Dacorum Borough Council, Development Management Committee webcast, 15 October 2026, for the vote, the proposer, seconder and abstentions, the two added conditions and the officer’s summing-up.
- Dacorum Borough Council, committee report for 25/01742/MOA, for the recommendation, the conditions on permission, the housing supply figure and the scheme.
- Dacorum Borough Council, meeting page, 15 October 2026.
Have your say